Back to projects

Allen Road installation of new 150 mm watermain to complete looping

Strathroy-Caradoc, Ontario

completeDrinking WaterCWWF
Federal contribution
$50,000
Federal share33%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 24, 2017(actual)
Construction end
Aug 11, 2018(actual)

Against the original forecast

  • Construction start15 months lateforecast May 1, 2016
  • Construction end4 months lateforecast Mar 31, 2018

Also in Strathroy-Caradoc

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48060 in the federal list. How to read these figures.