McKellar Street upgrade to 825 mm storm sewer and 200 mm watermain and replacement of 250 mm sanitary sewer

Strathroy-Caradoc, Ontario

completeWastewaterCWWF
Federal contribution
$448,656
Federal share21%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 26, 2018(actual)
Construction end
Jun 30, 2019(actual)

Against the original forecast

  • Construction start2.2 years lateforecast May 1, 2016
  • Construction end8 months lateforecast Oct 31, 2018