Langley-D - Yorkson Lowlands Stormwater Management and Ecological Restoration
Federal contribution
$692,744
Federal share40%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
today
202220232024202520262027
BuiltForecast
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Corporation of the Township of Langley
- Construction start
- Jun 1, 2027(forecast)
- Construction end
- Sep 30, 2027(forecast)