Fort Smith Trail and Basketball Court
Fort Smith, Northwest Territories
Federal contribution
$309,791
Federal share48%
of $642.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
2022
Built
Approved 2 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Fort Smith
- Construction start
- Jul 6, 2021(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction start11 months earlyforecast Jun 1, 2022
- Construction end8 months earlyforecast Nov 30, 2022
Also in Fort Smith
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60307 in the federal list. How to read these figures.