Fort St. John - North Peace Arena 2021 Upgrades

Fort St. John, British Columbia

completeRecreationCVRIS
Federal contribution
$687,200
Federal share80%

of $859.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Fort St. John
Construction start
Dec 15, 2021(actual)
Construction end
May 24, 2023(actual)

Against the original forecast

  • Construction start6 months earlyforecast Jun 20, 2022
  • Construction end5 months lateforecast Dec 31, 2022