Lhtako Dene Nation - Multi-use Pathway and Street Lighting Network Development
Federal contribution
$935,165
Federal share100%
of $935.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 3, 2021
202220232024
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Lhtako Dene Nation
- Construction start
- Sep 26, 2022(actual)
- Construction end
- Dec 14, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 13, 2022
- Construction end2 weeks earlyforecast Dec 30, 2023
Also in Quesnel
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60560 in the federal list. How to read these figures.