Dome Road Solar Independent Power Plant
Federal contribution
$485,895
Federal share66%
of $738.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- Arctic Energy Fund
- Ultimate recipient
- Klondike Development Organization
- Construction start
- Aug 18, 2021(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Sep 1, 2021
- Construction end2 months lateforecast Jan 25, 2022
Also in Dawson City
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60575 in the federal list. How to read these figures.