Cataraqui Trail Improvements
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
Built
Approved 3 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cataraqui Region Conservation Authority
- Construction start
- Oct 20, 2021(actual)
- Construction end
- Dec 15, 2021(actual)
Against the original forecast
- Construction start5 months lateforecast Jun 1, 2021
- Construction end2 weeks earlyforecast Dec 31, 2021