Replacement of 9th Concession Road Culvert

Rideau Lakes, Ontario

completeWastewaterCWWF
Federal contribution
$5,069
Federal share50%

of $10.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Rideau Lakes
Construction start
Aug 30, 2017(actual)
Construction end
Oct 10, 2017(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 10, 2017
  • Construction end3 months lateforecast Jul 11, 2017

Also in Rideau Lakes

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48706 in the federal list. How to read these figures.