Back to projects

Replacement of Sunnyside Road Culvert

Rideau Lakes, Ontario

completeWastewaterCWWF
Federal contribution
$16,794
Federal share50%

of $33.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Rideau Lakes
Construction start
Aug 29, 2017(actual)
Construction end
Oct 15, 2017(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jul 5, 2017
  • Construction end3 months lateforecast Jul 6, 2017

Also in Rideau Lakes

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48705 in the federal list. How to read these figures.