Replacement of Culverts/Ditching along Coons Road
Federal contribution
$10,006
Federal share50%
of $20.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2018
2018
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Rideau Lakes
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Sep 30, 2017(actual)
Also in Rideau Lakes