Robert Service School Modular Classrooms Expansion
Federal contribution
$5.6M
$5,648,298
Federal share100%
of $5.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 4, 2021
20222023
Built
Approved 2 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Government of Yukon
- Construction start
- Oct 5, 2021(actual)
- Construction end
- Jan 18, 2023(actual)
Against the original forecast
- Construction start7 weeks lateforecast Aug 15, 2021
- Construction end3 weeks lateforecast Dec 31, 2022