Back to projects

Street Upgrading - Chaytors Place

Conception Bay South, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$123,441
Federal share33%

of $370.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Rural & Northern Infrastructure Stream
Construction start
Jul 25, 2022(actual)
Construction end
Mar 6, 2023(actual)

Against the original forecast

  • Construction start9 months earlyforecast May 1, 2023
  • Construction end7 months earlyforecast Sep 30, 2023

Also in Conception Bay South