Topaz Park Artificial Turf Field
Federal contribution
$941,460
Federal share29%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
2023
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- The City of Victoria
- Construction start
- Jun 27, 2022(actual)
- Construction end
- Mar 28, 2023(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 13, 2022
- Construction end3 months lateforecast Dec 16, 2022
Also in Victoria
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61493 in the federal list. How to read these figures.