Quesnel - West Fraser Timber Park Trails
Federal contribution
$107,151
Federal share40%
of $267.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
2022202320242025
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Quesnel
- Construction start
- Jul 24, 2023(actual)
- Construction end
- Mar 31, 2025(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2023
Also in Quesnel
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61498 in the federal list. How to read these figures.