Humboldt Community Transit System
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 10, 2024
20232024
Built
Approved 2 years before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- City of Humboldt
- Construction start
- Sep 19, 2022(actual)
- Construction end
- Mar 31, 2023(actual)
Against the original forecast
- Construction start8 months lateforecast Jan 4, 2022
- Construction end9 months lateforecast Jun 30, 2022
Also in Humboldt
- City of Humboldt - Wastewater Treatment System Upgrades$14.7M
- Water Distribution Plant and Reservoir$1.4M
- Uniplex and High School Retrofit$973.2K
- City of Humboldt Storm Water Detention Pond$647.1K
- Regional Authority of Carlton Trail Waste Management District (REACT) - Phase 2 Decommissioning of REACT Waste Management Facility$583.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62143 in the federal list. How to read these figures.