Back to projects

Abbotsford - Biogas Upgrading Technology at the Joint Abbotsford-Mission Environmental System (JAMES) Plant

Abbotsford, British Columbia

approvedGreen EnergyGIS
Federal contribution
$1.3M
$1,287,000
Federal share20%

of $6.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 27, 2022
today
2022202420262028
BuiltForecast

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Abbotsford
Construction start
Mar 10, 2027(forecast)
Construction end
May 2, 2028(forecast)

Also in Abbotsford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62159 in the federal list. How to read these figures.