Staircase Linking Jacques-Cartier Avenue to Parc des Berges
Federal contribution
$90,000
Federal share44%
of $204.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 13, 2025
202320242025
Built
Approved 2.8 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Donnacona
- Construction start
- Nov 1, 2023(actual)
- Construction end
- Nov 30, 2024(actual)
Against the original forecast
- Construction start14 months lateforecast Aug 31, 2022
- Construction end2.1 years lateforecast Oct 31, 2022
Also in Donnacona
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63680 in the federal list. How to read these figures.