Ventilation and air conditioning of a sports complex at Cégep de Drummondville
Federal contribution
$76,046
Federal share21%
of $361.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2024
20232024
Built
Approved 2.2 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Drummondville
- Construction start
- Jun 19, 2023(actual)
- Construction end
- Nov 20, 2023(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Aug 1, 2023
- Construction end3 weeks lateforecast Nov 1, 2023
Also in Drummondville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63831 in the federal list. How to read these figures.