Ventilation and air conditioning of a sports complex at Cégep de Drummondville

Drummondville, Quebec

completeVentilationCVRIS
Federal contribution
$76,046
Federal share21%

of $361.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2024
20232024
Built

Approved 2.2 years before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep de Drummondville
Construction start
Jun 19, 2023(actual)
Construction end
Nov 20, 2023(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Aug 1, 2023
  • Construction end3 weeks lateforecast Nov 1, 2023

Also in Drummondville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63831 in the federal list. How to read these figures.