Replacement of humidifiers at Cégep de Saint-Jérôme
Federal contribution
$66,000
Federal share80%
of $82.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2024
20232024
Built
Approved 2.2 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Saint-Jérôme
- Construction start
- Jun 13, 2023(actual)
- Construction end
- Dec 8, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 3, 2023
- Construction end6 months lateforecast Jun 2, 2023
Also in Saint-Jérôme
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63834 in the federal list. How to read these figures.