Bicycle Network - Père-Lamarche, St-Rédempteur and William-Russell
Federal contribution
$162,025
Federal share21%
of $778.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 12, 2025
202320242025
Built
Approved 2.3 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Matane
- Construction start
- May 15, 2023(actual)
- Construction end
- Sep 22, 2024(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2023
- Construction end11 months lateforecast Oct 31, 2023
Also in Matane
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64204 in the federal list. How to read these figures.