Safety and Active Travel Upgrades for Fort Street, Victoria, BC
Federal contribution
$3.7M
$3,665,711
Federal share39%
of $9.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 17, 2023
20232024
Built
Approved 10 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- The City of Victoria
- Construction start
- Apr 13, 2023(actual)
- Construction end
- Dec 28, 2023(actual)
Against the original forecast
- Construction start8 months lateforecast Aug 8, 2022
- Construction end7 months lateforecast May 15, 2023