TransCanada Trail - West Bragg Creek Trail Paving Phase 3
Federal contribution
$190,131
Federal share60%
of $316.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 26, 2024
20232024
Built
Approved 23 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Bragg Creek Trails Association
- Construction start
- Aug 28, 2023(actual)
- Construction end
- Oct 18, 2023(actual)
Against the original forecast
- Construction start12 months lateforecast Aug 15, 2022
- Construction end12 months lateforecast Nov 1, 2022
Also in Rocky View County
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64246 in the federal list. How to read these figures.