Conception Bay South T'Railway Phase IV Construction
Conception Bay South, Newfoundland and Labrador
Federal contribution
$711,458
Federal share48%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2023
202320242025
Built
Approved 9 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Conception Bay South
- Construction start
- Apr 28, 2023(actual)
- Construction end
- Dec 20, 2024(actual)
Against the original forecast
- Construction start8 months lateforecast Aug 14, 2022
- Construction end15 months lateforecast Sep 14, 2023
Also in Conception Bay South
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64252 in the federal list. How to read these figures.