Walk Safe Pictou

Pictou, Nova Scotia

completeActive TransportationATF
Federal contribution
$46,200
Federal share60%

of $77.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 21, 2024
202320242025
Built

Approved 22 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Pictou
Construction start
Dec 23, 2022(actual)
Construction end
Jan 29, 2025(actual)

Against the original forecast

  • Construction start5 months earlyforecast May 31, 2023
  • Construction end15 months lateforecast Oct 30, 2023

Also in Pictou

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64290 in the federal list. How to read these figures.