King City GO Station Connection
Federal contribution
$86,101
Federal share38%
of $225.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 26, 2024
202320242025
Built
Approved 23 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Township of King
- Construction start
- May 18, 2023(actual)
- Construction end
- Aug 31, 2025(actual)
Against the original forecast
- Construction start3 months earlyforecast Sep 1, 2023
- Construction end5 months earlyforecast Jan 31, 2026
Also in King
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64319 in the federal list. How to read these figures.