Active Transportation Pathway Improvements for the University of Victoria

Victoria, British Columbia

completeActive TransportationATF
Federal contribution
$2.4M
$2,395,828
Federal share60%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 17, 2023
20232024
Built

Approved 5 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
University of Victoria
Construction start
Mar 1, 2024(actual)
Construction end
Nov 1, 2024(actual)

Against the original forecast

  • Construction start10 months lateforecast May 1, 2023
  • Construction end5 weeks lateforecast Sep 30, 2024