Back to projects

Active Transportation Network Assessment for the Transportation & Active Mobility Plan of The Township of Langley, British Columbia

Langley, British Columbia

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share83%

of $60.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 11, 2023
20232024
Built

Approved 7 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Township of Langley
Construction start
Mar 9, 2023(actual)
Construction end
Mar 31, 2024(actual)

Against the original forecast

  • Construction start4 months lateforecast Nov 1, 2022
  • Construction end5 months lateforecast Oct 31, 2023

Also in Langley