Coquitlam Walkway Planning: Staircase Inventory and Condition Assessment Study

Coquitlam, British Columbia

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2022
20232024
Built

Approved 8 weeks before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Coquitlam
Construction start
Jul 27, 2023(actual)
Construction end
Apr 22, 2024(actual)

Against the original forecast

  • Construction start5 months lateforecast Mar 1, 2023
  • Construction end9 months lateforecast Jul 24, 2023

Also in Coquitlam

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64530 in the federal list. How to read these figures.