Back to projects

Street Paving and Upgrading

Conception Bay South, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$662,349
Federal share33%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2024
202320242025
Built

Approved 19 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Aug 12, 2024(actual)
Construction end
Nov 7, 2025(actual)

Against the original forecast

  • Construction start8 months earlyforecast Apr 4, 2025