Mómeqwem Multi-use Pathway and McLennan Creek Active Transportation Crossing Feasibility and Design Study, Matsqui First Nation

Abbotsford, British Columbia

completeCapacity BuildingATF
Federal contribution
$49,950
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 15, 2023
20232024
Built

Approved 11 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Matsqui First Nation
Construction start
Jan 1, 2023(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast Sep 1, 2022
  • Construction end4 months lateforecast Sep 1, 2023

Also in Abbotsford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65637 in the federal list. How to read these figures.