Addition of an air conditioning and ventilation unit to the sterilization
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 9, 2024
2024
Built
Approved 19 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux des Laurentides
- Construction start
- Apr 3, 2023(actual)
- Construction end
- Nov 1, 2023(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Jun 1, 2023
- Construction end5 months lateforecast Jun 2, 2023
Also in Saint-Jérôme
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66728 in the federal list. How to read these figures.