Larry Olexiuk Field Artificial Turf & Kinex Arena Lifecycle Replacement
Federal contribution
$824,000
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 28, 2024
2024
Built
Approved 14 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of St. Albert
- Construction start
- Apr 1, 2023(actual)
- Construction end
- Oct 15, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Jan 2, 2023
- Construction end3 months earlyforecast Dec 31, 2023