New Cycling Improvements Along London Streets

London, Ontario

underwayActive TransportationPTIS
Federal contribution
$5.6M
$5,600,000
Federal share40%

of $14.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 11, 2024
today
2023202520272029
BuiltForecast

Approved 16 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Aug 8, 2023(actual)
Construction end
Mar 1, 2030(forecast)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 3, 2023

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66795 in the federal list. How to read these figures.