ECC - SD 43 - Eagle Ridge Elementary Ventilation Improvements

Coquitlam, British Columbia

completeVentilationCVRIS
Federal contribution
$746,208
Federal share80%

of $932.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 31, 2023(actual)
Construction end
Sep 15, 2023(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 1, 2023
  • Construction end2 weeks earlyforecast Sep 30, 2023

Also in Coquitlam

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66838 in the federal list. How to read these figures.