ECC - SD 43 - Eagle Ridge Elementary Ventilation Improvements
Federal contribution
$746,208
Federal share80%
of $932.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- School District 43 - Eagle Ridge Elementary
- Construction start
- Mar 31, 2023(actual)
- Construction end
- Sep 15, 2023(actual)
Against the original forecast
- Construction start2 months earlyforecast Jun 1, 2023
- Construction end2 weeks earlyforecast Sep 30, 2023
Also in Coquitlam
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66838 in the federal list. How to read these figures.