ECC - SD 33 - Strathcona Elementary Ventilation Improvements
Federal contribution
$233,149
Federal share80%
of $291.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 8, 2023
2024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- School District 33 - Strathcona Elementary
- Construction start
- Jul 1, 2023(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2023
- Construction end2 weeks lateforecast Dec 15, 2023
Also in Chilliwack
- Vedder Bridge Replacement$4.2M
- Chilliwack - Design and Construction of Organic Food Waste Receiving and Pre-Processing Station & Digester # 4$3.6M
- City of Chilliwack Wastewater Treatment Plant Biological Treatment Expansion Phase 2$3.6M
- Replacement of Sanitary Sewers$1.3M
- Chilliwack - Evans Road Connector$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66840 in the federal list. How to read these figures.