Back to projects

ECC - SD 33 - Strathcona Elementary Ventilation Improvements

Chilliwack, British Columbia

completeVentilationCVRIS
Federal contribution
$233,149
Federal share80%

of $291.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 8, 2023
2024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 1, 2023(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2023
  • Construction end2 weeks lateforecast Dec 15, 2023

Also in Chilliwack

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66840 in the federal list. How to read these figures.