Back to projects

Chaytors Road Forcemain Replacement and Gully Pond Lift Station

Conception Bay South, Newfoundland and Labrador

approvedWastewaterGIS
Federal contribution
$317,392
Federal share40%

of $793.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 5, 2024
today
202420252026
BuiltForecast

Approved 18 months before the announcement.

Program
Green Infrastructure Stream
Construction start
May 13, 2026(forecast)
Construction end
Aug 31, 2026(forecast)

Also in Conception Bay South

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67356 in the federal list. How to read these figures.