Retaining Wall Curling Street

Corner Brook, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$453,508
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2024
20242025
Built

Approved 11 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
City of Corner Brook
Construction start
Jun 3, 2024(actual)
Construction end
Jul 14, 2025(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jun 24, 2024
  • Construction end5 months earlyforecast Nov 30, 2025

Also in Corner Brook