Retaining Wall Curling Street
Corner Brook, Newfoundland and Labrador
Federal contribution
$453,508
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2024
20242025
Built
Approved 11 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- City of Corner Brook
- Construction start
- Jun 3, 2024(actual)
- Construction end
- Jul 14, 2025(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jun 24, 2024
- Construction end5 months earlyforecast Nov 30, 2025
Also in Corner Brook
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67360 in the federal list. How to read these figures.