Roof replacement
Federal contribution
$480,000
Federal share80%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2024
2024
Built
Approved 16 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- May 8, 2023(actual)
- Construction end
- Nov 21, 2023(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Jun 26, 2023
- Construction end3 weeks lateforecast Oct 31, 2023
Also in Mirabel
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67372 in the federal list. How to read these figures.