ECC - SD 70 - Eighth Avenue Elementary Ventilation Improvements
Port Alberni, British Columbia
Federal contribution
$104,038
Federal share80%
of $130.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2024
2024
Built
Approved 10 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- School District 70 - Eighth Avenue Elementary
- Construction start
- Sep 1, 2023(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2023
Also in Port Alberni
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67735 in the federal list. How to read these figures.