Grande Prairie - Pedestrian Links – Trail Resurfacing

Grande Prairie, Alberta

completeActive TransportationCVRIS
Federal contribution
$189,925
Federal share13%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 2, 2024
2024
Built

Approved 9 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Grande Prairie
Construction start
Jun 5, 2023(actual)
Construction end
Jul 17, 2023(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2023
  • Construction end5 months earlyforecast Dec 31, 2023

Also in Grande Prairie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67740 in the federal list. How to read these figures.