10projects·$99.2Mfederal of $151.3M eligible
Pond Inlet Water Treatment Plant - Construction Phase
$48.6MPond Inlet · Drinking Water
approved·approved 2024
Pond Inlet Marine Infrastructure
$30.0MPond Inlet · Marine
complete·approved 2016
Power Plant Infrastructure Upgrades in Rankin Inlet, Coral Harbour, Chesterfield Inlet and Pond Inlet
$6.2MChesterfield Inlet +3 · Green Energy
complete·approved 2019
Nunavut School Air Handling Unit Cleaning
$4.6MArctic Bay +24 · Ventilation
complete·approved 2022
Powerplant Infrastructure Upgrades in Pond Inlet, Clyde River and Whale Cove
$4.4MClyde River +2 · Green Energy
complete·approved 2019
Pond Inlet Community Hall
$2.1MPond Inlet · Recreation
complete·approved 2006
Pond Inlet's Men's Shelter
$1.5MPond Inlet · Affordable And Temporary Housing
underway·approved 2022
Water Treatment Plants in Arctic Bay, Grise Fiord, Pond Inlet, Rankin Inlet and Sanikiluaq Planning
$1.1MArctic Bay +4 · Drinking Water
complete·approved 2021
Pond Inlet Wellness Centre
$550.0KPond Inlet · Other
complete·approved 2022
Purchase of one vehicle for on-demand, ride-sharing service in Pond Inlet (Nunavut).
$150.0KPond Inlet · Public Transit
complete·approved 2022
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Pond Inlet Water Treatment Plant - Construction Phase Government of Nunavut | Pond Inlet | Drinking Water | approved | $48.6M | $77.4M | 2024 |
| Pond Inlet Marine Infrastructure Nunavut Ministry of Community and Government Services | Pond Inlet | Marine | complete | $30.0M | $41.2M | 2016 |
| Power Plant Infrastructure Upgrades in Rankin Inlet, Coral Harbour, Chesterfield Inlet and Pond Inlet Qulliq Energy Corporation (QEC) | Chesterfield Inlet +3 more | Green Energy | complete | $6.2M | $8.3M | 2019 |
| Nunavut School Air Handling Unit Cleaning Government of Nunavut | Arctic Bay +24 more | Ventilation | complete | $4.6M | $5.3M | 2022 |
| Powerplant Infrastructure Upgrades in Pond Inlet, Clyde River and Whale Cove Qulliq Energy Corporation (QEC) | Clyde River +2 more | Green Energy | complete | $4.4M | $8.6M | 2019 |
| Pond Inlet Community Hall Government of Nunavut | Pond Inlet | Recreation | complete | $2.1M | $6.6M | 2006 |
| Pond Inlet's Men's Shelter Hamlet of Pond Inlet | Pond Inlet | Affordable And Temporary Housing | underway | $1.5M | $1.5M | 2022 |
| Water Treatment Plants in Arctic Bay, Grise Fiord, Pond Inlet, Rankin Inlet and Sanikiluaq Planning Government of Nunavut | Arctic Bay +4 more | Drinking Water | complete | $1.1M | $1.1M | 2021 |
| Pond Inlet Wellness Centre Hamlet of Pond Inlet | Pond Inlet | Other | complete | $550.0K | $1.1M | 2022 |
| Purchase of one vehicle for on-demand, ride-sharing service in Pond Inlet (Nunavut). Hamlet of Pond Inlet | Pond Inlet | Public Transit | complete | $150.0K | $221.6K | 2022 |