6projects·$40.5Mfederal of $80.1M eligible
Highway 11/17 - 4 Lane Expansion, CPR Overhead at Ouimet to Dorion East Loop
$37.4MDorion · Highways and Roads
complete·approved 2016
Reconstruction of Dorion Road Hill
$2.9MMattawa · Highways and Roads
underway·approved 2020
Retrofit Dorion Loop Road Municipal Facilities
$80.0KDorion · Administration, Emergency and Public Works
complete·approved 2021
Rehabilitation of Ouimet Canyon Road Bridge
$72.2KDorion · Highways and Roads
complete·approved 2006
Reconstruction of open roadside ditches and culvert replacements on the Fish Hatchery Road
$49.8KDorion · Wastewater
complete·approved 2017
Township of Dorion Asset Management
$3.5KDorion · Capacity Building
complete·approved 2007
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Highway 11/17 - 4 Lane Expansion, CPR Overhead at Ouimet to Dorion East Loop Ontario Ministry of Transportation | Dorion | Highways and Roads | complete | $37.4M | $74.9M | 2016 |
| Reconstruction of Dorion Road Hill Town of Mattawa | Mattawa | Highways and Roads | underway | $2.9M | $4.8M | 2020 |
| Retrofit Dorion Loop Road Municipal Facilities Township of Dorion | Dorion | Administration, Emergency and Public Works | complete | $80.0K | $100.0K | 2021 |
| Rehabilitation of Ouimet Canyon Road Bridge Township of Dorion | Dorion | Highways and Roads | complete | $72.2K | $216.7K | 2006 |
| Reconstruction of open roadside ditches and culvert replacements on the Fish Hatchery Road Township of Dorion | Dorion | Wastewater | complete | $49.8K | $99.7K | 2017 |
| Township of Dorion Asset Management Township of Dorion | Dorion | Capacity Building | complete | $3.5K | $10.6K | 2007 |