6projects·$4.5Mfederal of $9.0M eligible
Town of Trenton - Trenton Park Redevelopment
$2.3MTrenton · Recreation
complete·approved 2019
Storm water separation stage 4b - phase 2
$856.0KTrenton · Wastewater
complete·approved 2016
Duke and Main St Combined Sewer Seperation
$603.1KTrenton · Wastewater
complete·approved 2015
Storm Sewer Separation-Phase 4B
$428.0KTrenton · Wastewater
complete·approved 2022
Smelt brook culvert replacement
$268.5KTrenton · Wastewater
complete·approved 2016
Storm Sewer Separation Study
$31.9KTrenton · Capacity Building
complete·approved 2009
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Town of Trenton - Trenton Park Redevelopment Town of Trenton | Trenton | Recreation | complete | $2.3M | $3.8M | 2019 |
| Storm water separation stage 4b - phase 2 Town of Trenton | Trenton | Wastewater | complete | $856.0K | $1.7M | 2016 |
| Duke and Main St Combined Sewer Seperation Town of Trenton | Trenton | Wastewater | complete | $603.1K | $1.8M | 2015 |
| Storm Sewer Separation-Phase 4B Town of Trenton | Trenton | Wastewater | complete | $428.0K | $1.1M | 2022 |
| Smelt brook culvert replacement Town of Trenton | Trenton | Wastewater | complete | $268.5K | $537.1K | 2016 |
| Storm Sewer Separation Study Town of Trenton | Trenton | Capacity Building | complete | $31.9K | $95.7K | 2009 |