6projects·$1.5Mfederal of $4.2M eligible
Rehabilitation of Rice Lake Drive
$1.0MCobourg · Highways and Roads
complete·approved 2009
Rehabilitation and replacement of three bridges
$338.3KCobourg · Highways and Roads
complete·approved 2005
HVAC Replacement
$80.0KHamilton · Ventilation
complete·approved 2021
Extension of culvert and addition of guard rails at concrete box culvert located on Lander Road
$40.0KHamilton · Wastewater
complete·approved 2017
Construction of new well at Municipal Office location to provide clean drinking water to the public
$10.0KHamilton · Drinking Water
complete·approved 2017
Township of Hamilton Asset Mangement
$5.0KHamilton · Capacity Building
complete·approved 2007
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Rehabilitation of Rice Lake Drive Township of Hamilton | Cobourg | Highways and Roads | complete | $1.0M | $3.0M | 2009 |
| Rehabilitation and replacement of three bridges Township of Hamilton | Cobourg | Highways and Roads | complete | $338.3K | $1.0M | 2005 |
| HVAC Replacement Township of Hamilton | Hamilton | Ventilation | complete | $80.0K | $100.0K | 2021 |
| Extension of culvert and addition of guard rails at concrete box culvert located on Lander Road Township of Hamilton | Hamilton | Wastewater | complete | $40.0K | $80.0K | 2017 |
| Construction of new well at Municipal Office location to provide clean drinking water to the public Township of Hamilton | Hamilton | Drinking Water | complete | $10.0K | $20.0K | 2017 |
| Township of Hamilton Asset Mangement Township of Hamilton | Hamilton | Capacity Building | complete | $5.0K | $14.9K | 2007 |