Improvements to Four Bridges
Federal contribution
$414,000
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Markstay-Warren
- Construction start
- Apr 26, 2005(actual)
- Construction end
- Oct 28, 2008(actual)
Against the original forecast
- Construction end4 months lateforecast Jun 30, 2008
Also in Markstay-Warren
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11813 in the federal list. How to read these figures.