Back to projects

Improvements to Highway 535

Markstay-Warren, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$112,319
Federal share45%

of $249.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Aug 4, 2010(actual)
Construction end
Jan 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 30, 2010
  • Construction end6 weeks lateforecast Dec 22, 2010

Also in Markstay-Warren