Upgrades to Markstay-Warren Community Centre

Markstay-Warren, Ontario

completeRecreationCC Top Up
Federal contribution
$150,667
Federal share33%

of $452.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Sep 1, 2010(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction start15 months lateforecast Jun 4, 2009
  • Construction end4 months earlyforecast Oct 31, 2011

Also in Markstay-Warren