Playground Improvements

Markstay-Warren, Ontario

completeActive TransportationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2021
202220232024
Built
Program
COVID-19 Resilience Stream
Construction start
Jul 3, 2023(actual)
Construction end
Jul 31, 2024(actual)

Against the original forecast

  • Construction end3 months lateforecast May 15, 2024