Increasing Warren Sewage Lift Station reliability by replacing two aging 10 horsepower lift pumps

Markstay-Warren, Ontario

completeWastewaterCWWF
Federal contribution
$12,190
Federal share49%

of $25.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
May 15, 2018(actual)
Construction end
May 31, 2018(actual)

Against the original forecast

  • Construction start13 months lateforecast Apr 1, 2017
  • Construction end6 months lateforecast Nov 30, 2017

Also in Markstay-Warren

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50176 in the federal list. How to read these figures.